Muncho Lake Alaska Highway Realignment
Location: Muncho Lake Provincial Park, Northern BC
Project Owner: PWGSC
Scope:
- 777,000m3 Embankment material for construction new alignment
- 105,000m3 Stripping topsoil material and organic material to stockpile and reuse as topsoil
- 20,000m3 Slope armouring material cut on slopes
- 60Ha Clearing of trees, bruch and other vegetation
- 2,000m Construction and riprap lining of drainage swales
- 800m Installation of drainage culverts (600mm to 1800mm) through multiple drainage channels
- Design-build 2.8m diameter drainage structure and 1450m2 MSE retaining wall for Ed’s Creek
- 160,650m2 Topsoil placement on completed slopes
- 40Ha Hydroseeding of slopes
Contract Value: $18 Million